Appleby

Blackoak have recently completed a caravan site consisting of 24 caravan bases. To begin we had to remove the original, old, dated caravan bases as well as the existing drainage and services. Once all the pads had been removed, we made sure we had a clean site ready to install all the new drainage, concrete bases, road construction; and all the finishing touches including block paving driveways, top soiling, and turfing. As can be seen in the photos, we take pride in everything we do. We did have to battle a lot of bad weather to ensure this job was completed on time, nevertheless we successfully met the deadline and completed the work to the highest of standards. Our moto at Blackoak is “That’ll do – Won’t do”

Value: £288,000
Duration: 24 Weeks