Maytree was a small job completed for one of our clients, which consisted of removing grassed areas by reduce digging to ensure we are down to good ground and then removing all soil and turf from site. We continued by laying a none-woven geotextile to prevent any weeds etc growing through. Type 1 MOT was used to stone up to the correct heights and levels, followed by tarmacking with base and topping layers. We at Blackoak like to ensure we tidy as we work and complete all works to the highest of standards. Looking at the second photo it shows how we have installed a footpath which was originally a small garden area. This was largely the same procedure as the footpath, reduce dig, laying geotextile, stoning up, and then laying flags on sand and cement.
Value: £14,400
Duration: 2 Weeks